In the afternoon of September 2th, 2019, Vice Chairman Vu Minh Hoang had a meeting with Bac Giang - Lang Son Expressway Project.
Mr. Vu Minh Hoang at the meeting with the Project Executive Board
At the meeting, Mr. Vu Minh Hoang suggested the Project Executive Board to continue to closely monitor the construction activities, especially actively remove some outstanding obstacles to proceed to complete the project as scheduled.
On the occasion of National Day, Vice Chairman Vu Minh Hoang also encouraged the officials and staffs of the project. “We have one more month to complete the stages for the unstoppable route. In the past, the Project Executive Board and all officials and staffs of the project has made already great efforts. Toward the opening of public traffic and putting the works into operation, we have to focus much more. In parallel with the completion of the remaining items of the project, the Project Executive Board has to coordinate with the localities to pay attention to the restoration work, stabilizing the people’s life, taking measures to protect the order and security and traffic safety throughout the project area,” Mr. Vu Minh Hoang emphasized.
Mr. Vu Minh Hoang and Mr. Nguyen Quang Vinh visited and gave presents to the officials and staff at the toll booth
As soon as meeting with the Project Executive Board, Vice Chairman Vu Minh Hoang and the General Director of Bac Giang - Lang Son Expressway Project, Mr, Nguyen Quang Vinh visited, encouraged and gave presents gifts to the officials and staffs at the toll booth of the project.
Based on the report of the Executive Board of Bac Giang - Lang Son BOT Company, the land acquisition was completely settled in August 2019, the construction progress reached 90% of total volume of the project. “The completion construction is ensured as scheduled, the quality meets the technical requirements and project requirements,” the Executive Board said.
Bac Giang - Lang Son BOT Company also said that, according to the plan of this project, the main routes will be completed on September 15th, 2019, completion of acceptance will be in October 2019, and completion of the toll collection procedure will be in December 2019.
Friendly Football Match
Previously, the State Acceptance Council was chaired by the Deputy Minister of Ministry of Construction, Mr. Le Quang Hung - Standing Vice Chairman of the Council visited and inspected the construction of Bac Giang Expressway - Lang Son Project on August 23rd, 2019. At the meeting, Deputy Minister of Ministry of Construction, Mr. Le Quang Hung commented: “Deo Ca Group is the biggest investor in the infrastructure investment, so we are assured. The inspection of routes shown that the quality is satisfactory up to now. However, the relevant agencies have to carry out an independent inspection to ensure the quality of construction”.
In the afternoon on the same day (September 2nd), the Executive Board of Bac Giang - Lang Son Expressway Project held a friendly football match and a friendly party between the Project Executive Board and the Office of Board of Directors of the Group.
The friendly and working day ended in the friendship and solidarity.