The North-South Expressway project in PPP form at the Cam Lam - Vinh Hao section is currently 2.2km away in Ninh Thuan province, which has not yet been handed over and faces difficulties related to material sources.
Deo Ca Group has fully mobilized equipment and finance to implement the Cam Lam - Vinh Hao Expressway Project (PPP)
Implementing the direction of the National Assembly and the Government on key tasks to complete on schedule the North-South Expressway through the area, including the Cam Lam - Vinh Hao Expressway Project, in the near future. Recently, Ninh Thuan province has actively worked with the Ministry of Transport and investors to remove difficulties and obstacles to speed up the project implementation.
At the meeting to remove difficulties for the Project on November 18, Mr. Le Huyen - Vice Chairman of Ninh Thuan Provincial People's Committee directed relevant departments, branches, and localities to focus on removing difficulties and supporting the project, and create favorable conditions for investors in the implementation process, especially the agreement on waste dumps and construction auxiliary areas to speed up the project implementation.
Regarding the handling of applications for licenses to exploit minerals as building materials, the Vice Chairman of Ninh Thuan Provincial People's Committee requested departments, agencies, and localities to actively speed up the processing of mining license applications, especially for material mines in Phuoc Huu and Phuoc Vinh communes, Ninh Phuoc district, proposed by the Investor in accordance with the spirit of Resolution No. 60/NQ-CP and 133/NQ-CP of the Government.
At the same time, the leader of Ninh Thuan province also assigned the Ninh Thuan Department of Construction to proactively provide periodic price announcements of construction materials according to regulations to investors and handle related issues to advise the Provincial People's Committee to direct. price control of construction materials in the province.
In addition, for the land acquired due to additional design adjustments, in the meeting on November 16, 2021, Mr. Phan Tan Canh - Vice Chairman of Ninh Thuan Provincial People's Committee directed the People's Committees of districts to focus on accelerating the progress of the project. completion, site clearance, and handover to the project enterprise in December 2021 to ensure the timely progress of the project.
"This is the last meeting to deal with problems related to site clearance of the project, the responsibility for site clearance belongs to the local government and coordinates with relevant units to implement timely and effectively," said Mr. Phan Tan. Scene emphasis.
Previously, at an online conference on the implementation of component projects on the East North-South Expressway for the period 2017-2020, held on September 14, 2021, by Deputy Prime Minister Le Van Thanh as a Chairman, he affirmed: "This is a national key project, playing a very important role in socio-economic development, ensuring national defense and security, serving the people's life. Therefore, the ministries and local branches must improve their roles and responsibilities, not to delay the completion schedule".
Also in this conference, the Deputy Prime Minister requested local authorities and relevant agencies to urgently direct local departments, agencies to minimize the time taken to process licensing and mineral extraction procedures construction materials, ensuring sufficient supply of materials for the project's construction in accordance with the Government's direction in Resolution No. 60/NQ-CP, promptly and fully promulgating the appropriate construction price index in line with the reality of market fluctuations and the nature of the project and take full responsibility before the Government and the Prime Minister for the progress of site handover.
Cam Lam - Vinh Hao expressway project is 78.5km long, phase 1 invests in a scale of 4 lanes, 17m roadbed, design speed 80km/h. The project has a total investment capital of 8,925 billion VND by Deo Ca Group as the representative of the investor consortium. Up to now, the project has arranged enough capital including equity capital and other mobilized capital to carry out the construction.
BY BAO NHU