On the construction site of Cua Luc 1 Bridge

04/09/2020     888

The first project connecting Ha Long - Hoanh Bo after the merger, Cua Luc 1 bridge, is speeding up the basement items by contractors. Up to now, after 4 months of construction, the entire main bridge bored pile system has been completed, the contractor has started the construction of the pier body and bridge abutment.

Cua Luc 1 Bridge and the leading roads have a total length of 4,265m. In which, the main bridge is designed in the form of steel tube arch filled with concrete with 6 lanes, 33.1m wide, 290m long, 40x7m of navigational clearance.

The main bridge bored pile system has been completed, the contractor started to the construction of the pier body and bridge abutment according to the schedule.

In which, T2 pillar has been poured concrete of the transverse brace, T3 pillar poured concrete the body of phase 2, T6 pillar has installed the reinforcement base, etc.

The item of leading road on the Hoanh Bo area is in the progress of bored pile construction.

Pouring soil to make service road for the leading road item on Hoanh Bo area.

Currently there are more than 100 officials and workers constructing simultaneously at 4 locations. It is expected that in January 2021, the entire main girder of the main bridge will be completed; in July 2021, the main bridge steel arch system will be completed; in October 2021, completing the construction of concreted steel tube; Other items such as access bridges, bridges on the route and leading roads will be carried out parallel to the main bridge.

The perspective of Cua Luc 1 Bridge after completing construction in 2021.

By DO PHUONG