With the onset of the rainy and stormy season, heavy rainfall persists in the central provinces. Despite facing numerous adverse weather conditions, the engineers and laborers at the Quang Ngai - Hoai Nhon project site remain steadfastly committed to their work, ensuring the timely progress of the construction.
The Quang Ngai - Hoai Nhon project, spanning 88km, is divided into 3 construction packages, led by Deo Ca Group in collaboration with other contractors. Currently, 39 out of 41 construction sections along the entire route are actively being worked on.
20:00, Tunnel Entrance Number 1 (Package XL2) brightly illuminated with construction lights for night work
The route consists of three mountain tunnels. For tunnel construction tasks, engineers and workers take shifts to work continuously (24/24) without breaks.
The progress of tunnel excavation for Tunnel 1 has reached 241 out of 610 meters, and the left tunnel has been excavated to a length of 67 out of 610 meters.
Mr. Pham Thanh Doan, the safety engineer of Tunnel 1, mentioned that due to heavy rain, the management board continuously reminds and strengthens safety control, particularly focusing on the electrical system and the storage of materials to prevent safety hazards and material damage.
Deep within the mountain, the workers and engineers are tirelessly dedicated to their tasks.
At 11 PM, engineers and workers in Tunnel 1 are still diligently drilling and installing reinforced concrete anchors
Taking advantage of favorable weather conditions, Deo Ca Group is focusing on accelerating the tunnel construction tasks, aiming to work inside the tunnels and avoid the impacts of rain and storms.
At 4 AM, in the northern section of Tunnel 3 (Pho Khanh commune, Duc Pho district, Quang Ngai), workers are currently carrying out tunnel reinforcement by spraying concrete
After each round of concrete spraying inside the tunnel, the drilling equipment is taken outside and thoroughly cleaned, ready for the next round of construction
In the extremely confined space, the organization of construction work must be highly professional, including coordination of machinery, equipment, personnel, and construction measures, to ensure absolute safety.
The group of workers is currently installing pipe anchors to create openings for the drilling machine in Tunnel 2
Tunnel construction is a highly technical task that demands strict adherence to safety standards in labor. The management board regularly disseminates information, raises awareness, and reminds workers about safety measures. Additionally, alcohol concentration tests are conducted prior to starting work shifts.
Alcohol concentration tests are conducted prior to the commencement of every work shift, ensuring strict adherence to safety protocols
In contrast to tunnel construction, the organization of road and bridge construction encounters various challenges during the rainy season, requiring meticulous planning and execution.
At the location of Song Ve Bridge, the gathering of materials, machinery, and equipment, as well as the organization of construction activities, are closely monitored
With a length of over 610m, Song Ve Bridge is one of the crucial components of Package XL1. During the rainy and stormy season, the construction organization is significantly impacted. In addition to ensuring progress, the management board of the project package prioritizes electrical safety measures, tensioning of foundation warning wires, and monitoring water levels at bridges and culverts to ensure labor safety.
The engineers not only engage in construction work but also closely monitor weather conditions and water levels of the Song Ve River. This allows them to promptly report any changes to the Command Board and propose necessary measures for handling the situation
The inspection of reinforced steel components of drilled and filled piles is conducted
Mr. Nguyen Vu Khoa, the Chief Commander of Song Ve Bridge construction, mentioned that during the rainy season, organizing construction activities on-site encounters significant challenges. They have to seize favorable weather conditions to accelerate construction progress by arranging overtime shifts or continuous work to compensate for the time lost due to rain and storms. As a result, the project's progress has been able to meet the set requirements up to this point.
Taking advantage of rain-free days, the XL1 package construction section passing through Nghia Hanh district (Quang Ngai) has the contractor organizing overnight construction activities
In addition to weather challenges, land clearance is also a significant challenge for the contractor. While there may not be a large amount of remaining land to be cleared, the uneven distribution of clearance areas poses difficulties in implementing synchronized construction activities.
BY LAM TRA - THE SON